Capture

6th Conference of Croatian Geotechnical Society was held in Zadar, 17-19 October 2013. Papers, written mostly in Croatian with abstract in English, can be found in this page.

Title page
Impressum
Content
Sponzors

INVITED LECTURES

  • Tanja ROJE-BONACCI: Vajont (1963.-2013.) and E. Nonveiller Case Study, 2-11
  • Zvonimir SEVER: Peruća Dam – Destruction and Reconstruction, 12-28

PAPERS

  • Zlatko BRŠČIĆ, Leo MATEŠIĆ, Ivan MIHALJEVIĆ: Guidelines for preparation of the technical regulation on monitoring of large dams, 30-35
  • Leo MATEŠIĆ, Ivan MIHALJEVIĆ: Monitoring of structures after construction in accordance with, Eurocode 7, 36-41
  • David KNEIFL, Mladen MIKEC: Soil stabilization using triaxial geogrids, 42-47
  • Christian PSIORZ, Mario MARIC, Jörg KLOMPMAKER: Geogrid reinforced railway embankments on soft soils Experiences from field measurements, 48-52
  • Christian PSIORZ, Mario MARIC, Jörg KLOMPMAKER: Design principles for geogrid reinforced steep slopes under consideration of monitoring results, 53-58
  • Luka SORIC, Predrag KVASNIČKA, Marinko MAROHNIĆ, Karolina GRADIŠKI: Sv. Trojica reinforced earth wall – back analysis for the state shortly after construction, 59-64
  • Ida ALEKSIĆ, Igor SOKOLIĆ, Pero ŠIŠA: Railway rockfall slope protection,   65-72
  • Mirko GROŠIĆ, Željko ARBANAS: Određivanje parametara puzanja fliša temeljem višegodišnjeg praćenja ojačane padine, 73-81
  • Željko MIKLIN, Tomislav NOVOSEL, Željko SOKOLIĆ, Petra KOSORIĆ, Ivana DOBRILOVIĆ: Structural borehole T-300 and its significance in modelling of Sljeme foothill Zone: 82-88
  • Predrag MIŠČEVIĆ, Goran VLASTELICA, Daša SALVEZANI: maintenance of slope surfaces excavated in soft rock, 89-94
  • Igor SOKOLIĆ, Ivan GALIĆ, Neven KRALJ: Settlement measurements by using horizontal inklinometers and vertical deformeters, 95-102
  • Luka ZUBČIĆ, Igor SORIĆ: Blasting of the underwater reef in front of the new port of the city of Zadar, 103-107
  • Krunoslav MINAŽEK: Geotehnical measurements at foundation remediation of Vukovar highschool, 108-115
  • Kristijan LJUTIĆ, Sergije BABIĆ, Petra BUTORAC: Recording current state of county roads retaining walls of the Primorsko-goranska county via GIS, 116-123
  • Ivan BRADVICA: High retaining wall and its alternative, 124-125
  • Goran DAŠIĆ, D. ŠAFAR, Goran GRGET, Katarina RAVNJAK: Šumetlica dam: site investigation, design and monitoring, 126-136
  • Krešo IVANDIĆ, Željko LEBO: Technical monitoring and maintenance of anchored reinforced concrete diaphragm wall “Moj Dvor” in Zagreb, 137-144
  • Marina BOŠKOVIĆ, Ana ŠIMUNOVIĆ, Biljana KOVAČEVIĆ ZELIĆ, Dubravko DOMITROVIĆ:

    Design of tilt table prototype and conducting pre-testing on

    geosynthetic samples

    145-151

  • Željko LEBO, Franjo VERIĆ: Rehabilitation of landslide “Dunjevac” in Zagreb, 152-159
  • Ivan MATKOVIĆ, Marko BIŠĆAN, Krunoslav MAVAR: Remediation of the church in Okić – example of preserving the architectural heritage, 160-165
  • Tanja ROJE-BONACCI: Usoi Dam, the higest dam on the Earth, 166-172
  • Miro JUKIĆ, Željko SOKOLIĆ: Technical survey of water recharge and drainage as oneof the basic element in strategy of slope remediation, 173-179
  • Bruno ŠKACAN, Davorin ŠINDLER, Dragan BUDIMIR, Milivoj KOS: grouting curtain for Reservoir Dam Ponikve, 180-185
  • Čedomir BENAC, Igor RUŽIĆ , Martina VIVODA, Sanja DUGONJIĆ JOVANČEVIĆ, Petra ĐOMLIJA: Susceptibility of coastal slopes to marine erosion and landsliding (South-western coast of Krk island), 186-192
  • Alberto PASQUETTO, Gianluca VINCO: Analytical modelling of the soil improvement by injections of high-expansion pressure Uretek resin, 193-198
  • Robert GOTIĆ, Mario HOHNJEC, Vlado HUDOLETNJAK, Slaven JAGAČIĆ: A coastal collector for the city Pula – construction technology for protection of construction pit, 199-207